以上海重型机器厂万吨水压机车间改建工程为例,对原有车间进行了抗震检测和鉴定;设计采用新结构与原有结构连成一个结构单元的方案,解决了新扩柱距无法设置柱间支撑的难题,新老结构连成一体后,在计算和构造上均满足现有规范的要求。
Taking the reconstruction engineering of 10 000 ton hydraulic press workshop of Shanghai heavy machinery plant as an example, the paper carries out anti-seismic detection and identification of original workshop, and designs a structural unit scheme by integrating new structure with original structure. As a result, it solves the hard issue of setting column of new expansion column distance. The integrity of new and old structure meets the structural and calculation demands.
出处
《山西建筑》
2012年第23期36-38,共3页
Shanxi Architecture
关键词
抗震鉴定
抗震构造措施
吊车梁计算
抗震计算
anti-seismic appraisal, anti-seismic structural measure, crane girder calculation, anti-seismic calculation