摘要 土挤密桩法是利用沉管、冲击或爆扩等方法在地基中挤土成孔,然后向孔内夯填素土(一般为粘性土)成桩,通过成孔过程中的侧向挤压作用,桩孔内的土被挤向周围,使得桩间土得以挤密,消除黄土的湿陷性。用理论计算的方法分析土挤密桩的主要设计参数(孔间距),通过试验施工进行验证,选择合理的设计参数。研究结果对黄土地区的地基处理具有重要的指导作用。 Soil compaction pile method is using the immersed tube or shock or explosive with expanding to make holes in foundation.And then to fill the hole with Grain soil into pile,through the effect processed on the lateral extrusion in the hole making,its soil in hole was crowed into the surrounding,making the soil between piles to compaction and eliminating loess collapsibility.This paper analyzes the main design parameters(hole spacing) during the soil compaction pile method by theoretical calculation method,which was verified through the test construction,and chooses the reasonable design parameters.The conclusions have important guiding role for the foundation treatment of loess areas.
出处 《水科学与工程技术》 2012年第3期69-71,共3页 Water Sciences and Engineering Technology
关键词 黄土 湿陷性 理论计算 挤密桩 loess; collapsible; theoretical calculation; compaction pile
  • 相关文献

参考文献5

  • 1GB50025-2004.湿陷性黄土地区建筑规范[S].[S].,..
  • 2JGJ79-2002.建筑地基处理技术规范[S].,2002..
  • 3河北省水利水电第二勘测设计研究院.南水北凋中线漳古段SG3标湿陷性黄土处理技术要求[R].2011.
  • 4河北省水利工程局.SG3标湿陷性黄土土挤密桩试验报告[R].2012.
  • 5GB/T50123-1999.土工试验方法标准[S].[S].,..

共引文献1899

同被引文献5

  • 1GB50487-2008,水利水电工程地质勘察规范[S].
  • 2CECS246-2008,给水排水工程顶管技术规程[S].
  • 3GB50025-2004.湿陷性黄土地区建筑规范[S].[S].,..
  • 4保定市水利水电勘测设计院.保定市南水北调配套工程水厂以上输水管道工程可行性研究工程地质勘察报告[R].2012.
  • 5王建权.南水北调中线工程石家庄段黄土状土湿陷性研究[J].水科学与工程技术,2011(1):71-72. 被引量:1