基于MCCAA的工期成本质量的多目标优化分析 被引量:3

Multi-objective Optimization Analysis of Duration-cost-quality Based on MCCAA
在线阅读 下载PDF
导出
摘要 工期、成本、质量是工程建设项目的三大控制目标,然而这"三大目标"既对立又统一。为了同时达到三个目标的优化,构建合理的目标模型,并且针对传统蚁群算法容易出现早熟和停滞现象的缺陷,提出了一种改进的协同进化蚁群算法。在必要路段使各目标的信息素信息进行杂交变异,优化路径上的信息素分布,并运用改进的多种群蚁群协同算法实现算例的多目标优化应用。 The duration, cost, and quality are the three objectives of the construction project to control. However, the three main objectives are not only consistent but also opposite. In order to achieve the optimization of the three objectives, a reasonable target model is constructed. Furthermore, to overcome the default of precocity and stagnation in classical ant colony algorithm, an modified co-evolution ant colony algorithm is presented. The phero- mone information of which is conducted hybridization and variation in the necessary sections to optimize the phero- mone distribution of path. Finally the mentioned model and algorithm are applied to solve an example of multi-objective optimization.
作者 代逸生 刘媛
出处 《科学技术与工程》 北大核心 2012年第19期4676-4680,共5页 Science Technology and Engineering
基金 江苏省自然科学基金项目(SBK200930338)资助
关键词 蚁群算法 多种群 多目标优化 ant colony algorithmmulti-colonymulti-objectiveoptimization
  • 相关文献

参考文献6

二级参考文献44

  • 1张树义.协同进化(一)──相互作用与进化理论[J].生物学通报,1996,31(11):35-36. 被引量:11
  • 2杨波,万仲平,尹德玉.资源约束项目排序问题的一种修正蚁群算法[J].工程数学学报,2007,24(3):437-445. 被引量:4
  • 3Cohen M A, Jehoshua E, Ho T H. New product development: The performance and time-to-market trade-off[J]. Management Science, 1996, 42(2) : 173- 186.
  • 4Dawson D W, Askin R G. Optimal new product design using quality function deployment with empirical value functions [ J ]. Quality and Reliability Engineering, 1999, 15(1): 17 -32.
  • 5Tareghian R H, Taheri S H. On the discrete time, cost and quality trade-off problem[J]. Applied Mathematics and Computation, 2006, 181(2): 1305-1312.
  • 6Kis T. A branch-and-cut algorithm for scheduling of projects with variable-intensity activities [ J ]. Mathematical Programming, 2005, 103(3): 519-539.
  • 7Kolisch R. Serial and parallel resource-constrained project scheduling methods revisited: Theory and computation[J]. European J of Operational Research, 1996, 90(2): 320-333.
  • 8姚敏.最大关联隶属原则及其应用[J].控制与决策,1991,6(4):283-287.
  • 9Bonabeau E, Dorigo M, Theraulaz G. Inspiration for Optimization from Social Insect Behavior. Nature, 2000, 406(6791): 39-42.
  • 10Bonabeau E, Dorigo M, Theraulaz G. Swarm Intelligence:From Natural to Artificial Systems. New York, USA: Oxford University Press, 1999.

共引文献174

同被引文献25

  • 1王勇.风电工程建设中的管理模式及风险因素分析[J].风能,2010(11):34-37. 被引量:17
  • 2Tareghian H R, Taheri S H. On the discrete time, cost and quality trade-off problem[J]. Applied Mathematics and Computation, 2006,181 (2) :1305-1312.
  • 3Chen C H, Chong Y T, Chang W C, et al. A quality - time - cost -oriented strategy for product conceptualization[J]. Advanced Engineering Informatics, 2012, 26(1) :51-52.
  • 4Eshtehardian E, Afshar A, Abbasni R, et al. Fuzzy-based MOGA approach to stochastic time-cost trade-off problem[J] . Automation in Construction, 2009, 18 (5) : 692-701.
  • 5Yang. IT. Stochastic time-cost tradeoff analysis: A distribution-free approach with focus on correlation and stochastic dominance[J] . Automation in Construction, 2011, 20(7) :916-926.
  • 6SzmerekovskyJ G, Venkateshan P. An integer programming formulation for the project scheduling problem with irregular time - cost tradeoffs[J]. Computers & Operations Research, 2012,39 (7) : 1402-1410.
  • 7Ghoddousi P, Eshtehardian E,Jooybanpour S, et al. Multi-mode resource-constrained discrete time - cost-resource optimization in project scheduling using non-dominated sorting genetic algorithm[J]. Automation in Construction, 2013 ,30( I) :216-227.
  • 8Janss G F E, Lucas M, Whitfield D P, et al. The precautionary principle and wind-farm planning in Andalucia[J]. Biological Conservation, 2010,143(8): 1827-1828.
  • 9Muthuselvan N B, Devesh R M, Somasundaram P. Cauchy?Gaussian Infused Particle Swarm Optimization for Economic Dispatch with Wind Power Generation[J]. International Review of Electrical Engineering-IREE, 2011, 6(1) : 387-395.
  • 10Xu R, Chen H P, Li X P. A bi-objective scheduling problem on batch machines via a Pareto-based ant colony system[J] . InternationalJournal of Production Economics, 2013, 145 (I) : 371-386.

引证文献3

二级引证文献5

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部