摘要
介绍了王庄煤矿在 432 6超长壁综放工作面安装时 ,由于工作面所需设备在安装地点的位置、空间的特殊性 ,决定了各设备运入工作面的路线及先后顺序。通过对安装工序所需时间、人员进行优化 ,绘制出安装工序网络图。实践应用证明 ,该统筹规划合理可行 ,现场实践达到了快速安装的目的。
This paper introduces superlong fulling mechanized workface assembled in Wangzhuang coal mine.Because particularity of place,space when equipment is assembled in workface,it desides route and early or late order of equipment transported to workface.Through assembling process takes time,the people optimized,making out assembling process network chart.Practice and application proving:this overall planning is rational and workable practice achieves the goal for quick assembling.
出处
《煤》
2000年第2期24-26,57,共4页
Coal
关键词
综放工作面
设备安装
工序优化
统筹规划
综采
fuling mechanized workface
assembling of equipment
process optimized