工程进度控制关键链法应用分析 被引量:11

Application Analysis of Critical Chain Project Management for Schedule Control
在线阅读 下载PDF
导出
摘要 为了将工程进度控制最新理论成果——关键链法(CCPM)推广及应用到建筑工程项目,给工程项目管理人员提供一种新的方法,深度挖掘了关键链法的理论基础,并对该方法的应用步骤作出了具体的介绍。通过利用Crystal Ball软件对某一工程实例的预测分析,证明了关键链法在保证项目工期上明显优于传统进度控制方法,因此关键链法在建筑工程项目进度控制上具有广阔的应用前景。 To extend the application of the latest achievement in the engineering schedule control theory, the critical chain project management (CCPM) is introduced to the project schedule management of construction. The theory of CCPM is thoroughly investigated, and its procedures are introduced in detail, so as to provide an innovative thinking for decision making and management. Based on a practical example and analysis by Crystal Ball, the advantages of CCPM are obviously shown. Therefore the construction time limit can be guaranteed. The potential of CCPM is thus shown.
出处 《工程管理学报》 2012年第3期71-74,共4页 Journal of Engineering Management
关键词 关键链法 工程进度控制 多项目管理 缓冲 critical chain project management schedule control multi-project management buffer
  • 相关文献

参考文献6

二级参考文献25

  • 1刘士新,宋健海,唐加福.基于关键链的资源受限项目调度新方法[J].自动化学报,2006,32(1):60-66. 被引量:64
  • 2单汨源,龙颖.一种关键链缓冲机制改进方法及其应用研究[J].项目管理技术,2006,4(9):32-35. 被引量:21
  • 3Jeffrey Elton, Justin Roe. Bringing discipline to project management[J]. Harvard Business Review, 1998, (3/4): 153-159.
  • 4Gramham K Rand. Critical chain: the theory of constraints applied to project management [ J ] . International Journal of Project Management, 2000, 18: 173-177.
  • 5Steyn H. An investigation into the fundamentals of critical chain project scheduling [ J ]. International Journal of Project Management,2000, 19: 363-369.
  • 6Steyn H. Project management application of the theory of constraints beyond critical chain scheduling[J]. International Journal of Project Management, 2002, 20: 75-80.
  • 7Larry P Leach. Critical chain project management improve project performance[J]. Project Management Journal, 1999, 14: 312-322.
  • 8Wei Chiu-Chi, Liu Ping-Hung, Tsai Ying-Chin. Resource-constrained project management using enhanced theory of constraint [J]. International Journal of Project Management, 2002, 20: 561-567.
  • 9Elmaghraby SE, Herroelen WS, Leus R. Note on the paper 'Resource-constrained project management using enhanced theory of constraint' by Wei et al. [ J ]. International Journal of Project Management, 2003, 21: 301-305.
  • 10Willy Herroelen, Roel Leus. On the merits and pitfalls of critical chain scheduling [ J ]. Journal of Operations Management, 2001,(19): 559-577.

共引文献18

同被引文献64

引证文献11

二级引证文献30

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部