摘要
藏木水电站是西藏"十一五"规划重点项目,也是西藏第一座大型水电站,是西藏电力发展史上由建设10万千瓦级水电站到建设50万千瓦级水电站的标志性工程。藏木水电站工程设有四台LQP20/25t平移式缆索起重机,是大坝施工的主要起重设备,而10 kV缆机箱式开关站则是四台缆机运行的心脏,因此开关站的安装施工质量显得尤为重要。通过阐述箱式开关站的安装施工方法,对类似工程安装工作及其施工方案的编写具有一定的参考价值和借鉴作用。
Zangmu hydraulic power plant is not only one key project of Xizang Eleven five programming, but also is the first large-scale hydropower stations in Xizang. It's a symbolized project in the history of Xizang Power development by buliding from one hundred thousand kilowatts to five hundred thousand kilowatts. Reservoir hydropower project is equipped with four LQP20/25t translational type cable crane, which is used to the main lifting equipment of the dam construction. While the 10 kV cable box switch station is the four station cable machine running in the heart. Thus the switching station installation quality appears particularly important. Through elaborating the box switch station installation construction method for similar projects, installation and construction plan compiling has certain reference value and draw lessons from action.
出处
《上海第二工业大学学报》
2012年第2期127-134,共8页
Journal of Shanghai Polytechnic University
关键词
10kV
箱式开关站
安装
调试
施工措施
10 kV
box switch station
installation
debug
construction measures