重钢150t/h干熄焦装置烘炉实践与分析 被引量:1

Analysis and Practice of Oven Heating-up of the 150 t/h Coke Dry Quenching(CDQ) Equipment for Chongqing Steel
在线阅读 下载PDF
导出
摘要 介绍了重钢1#干熄焦烘炉过程,包括烘炉前期的准备工作、温风干燥阶段、煤气烘炉过程和投入红焦转入正常生产过程等操作的关键控制点,总结了烘炉过程中出现的问题及解决方案。 The heating up process of the No. l CDQ (coke dry quenching) oven of the Chongqing Steel was intro- duced, the preparation process before heating up, the warm air drying process, the COG heating up process and the red- hot coke charge process followed by the normal operation process were also expatiated. The key control points at various stages were reported and the problems occurred during heating-up and their solutions were summarized.
作者 倪菠 刘杰
出处 《煤化工》 CAS 2012年第3期34-37,共4页 Coal Chemical Industry
关键词 干熄焦 烘炉 温风干燥 煤气烘炉 红焦投入 CDQ (coke dry quenching), oven heating-up, warm-air drying, COG heating up, red-hot coke charging