摘要
针对近年来风电行业竞争激烈的局面,保质量、降成本、提效率是整机生产厂的主要应对措施。提出了一种风力发电机组出厂测试方案,保证机组出厂质量,以避免二次吊装,并减少风场调试的工作量,提高调试效率。
Regarding the keen competition in wind power industry in recent years, the main countermeasures are to assure quality, reduce cost and improve efficiency. A plant test project has been put forward for wind turbine to ensure its delivery quality, avoid twice hoisting assembly, reduce relevant commissioning work and increase the commissioning efficiency
出处
《发电设备》
2012年第3期204-206,共3页
Power Equipment
关键词
风力发电
出厂测试
变桨试验
偏航试验
静态测试
动态测试
wind power generation
plant test
variable pitch test
yawing test
static test
dynamic test