后云台山隧道下穿楼房近接施工控制爆破技术 被引量:6

Controlled Blasting Technology for Houyuntai Mountain Tunnel Construction Undercrossing Adjacent Building
在线阅读 下载PDF
导出
摘要 连云港东疏港高速公路控制性工程后云台山隧道,进口段处于密集建筑群地段,其中有1栋5层居民楼位于其上方,设计要求施工通过此地段时,爆破振动的速度要控制在2 cm/s以下,给隧道施工提出了极大的挑战。通过对下穿楼房的后云台山隧道采用控制爆破技术,并进行爆破试验及监测,优化爆破参数,最终确保了新建隧道的施工进度和既有建筑结构的安全。 Houyuntai Mountain Tunnel is the controlling project of Dongshugang-highway in Lianyungang.The entrance region is located in a dense building area,including a 5-story residential building located in its upper.During construction through this area,according to the design requirements,the blasting vibration velocity should be controlled under 2 cm/s or less.The requirements have raised a great challenge to the tunnel construction.With the method of controlled blasting technology,combing with blasting test and monitoring,and by optimizing blasting parameters,the construction progress of the new tunnel and structural safety of existing buildings are finally ensured.
作者 刘伟
出处 《石家庄铁道大学学报(自然科学版)》 2012年第1期63-67,共5页 Journal of Shijiazhuang Tiedao University(Natural Science Edition)
关键词 隧道 下穿楼房 近接施工 控制爆破 tunnel under passing residential building adjacent construction controlled blasting
  • 相关文献

参考文献5

二级参考文献36

共引文献245

同被引文献40

引证文献6

二级引证文献61

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部