摘要 依据浦东新区生活垃圾产量、组分及热值等,1998年底动工兴建日处理生活垃圾1000t规模的焚烧厂,占地8hm^2,工程总建筑面积22197m^2,投资估算66915万元(人民币)。主要焚烧设备采用SITY-2000倾斜往复阶梯式机械炉排等,配置有3条生产线,2套8500kW的汽轮发电机组。设计采用先进的焚烧工艺,自动化运行控制;按工厂寿命30a计,平均每吨生活垃圾处理成本150元,运行成本100元。建设垃圾焚烧厂具有较好的社会、经济和环境效益。 Based on the production components and thermal value of municipal solid waste in Pudong New Area, Shanghai, to construct an incineration plant for treating 1000t/d solid waste, which occupied 8hm2 land, total area of the project was 22197m2, with approxm. $669.15 million (RMB) investment in the end of 1998. The main equipment of the plant adopted SITY-200 type slant and moving and stairs type grate with three incineration lines, and two sets of 8500kW steam turbine generator, and design with advanced process, automatic performance control; estimating 30 years as life-span, the average capital costs for treating one ton of solid waste will be $150 with $100 cost of performance. The construction of incineration plant might have effective social, economic and environmental benefits.
作者 张静
出处 《上海环境科学》 CAS CSSCI CSCD 2000年第1期37-39,共3页 Shanghai Environmental Sciences
基金 上海市重大工程项目(国外贷款) 项目编号:X96000303246。
关键词 生活垃圾 焚烧 工程实例 浦东新区 垃圾处理厂 Domestic waste Incineration Real case of project Pudong New Area
  • 相关文献

参考文献1

二级参考文献3

  • 1陈雪英,环境科学研究,1995年,5期
  • 2马广大,大气污染控制工程,1995年
  • 3屈超蜀,重庆环境科学,1992年,4期

共引文献8

同被引文献109

引证文献18

二级引证文献252

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部