500kV线路避雷器和电容式电压互感器不拆线试验方法探讨 被引量:2

Discusses on the Test Method for 500 kV Transmission Line Arrestor and coupling capacitor voltage transformer without Removing Connecting Lead
在线阅读 下载PDF
导出
摘要 从多年试验实践出发,探讨了变电站站内500 kV线路避雷器和电容式电压互感器不拆除高压引线进行试验的方法。该方法可大大减轻高压线路拆接线工作量,并获得准确可信的测试结果,对线路避雷器和电容式电压互感器的试验有积极的指导意义。 The paper discusses a test method for 500 kV transmission line arrestor and coupling capacitor voltage transformer in substations which without removing high voltage connecting lead,based on test practices for many years.The method can greatly relieve workload of removing and connecting HV line lead and obtain accurately credible testing results at the same time.And it is positive to test on line surge arrester and coupling capacitor voltage.
作者 刘毅
机构地区 广州蓄能水电厂
出处 《大众科技》 2012年第3期122-124,135,共4页 Popular Science & Technology
关键词 避雷器 电容式电压互感器 试验方法 不拆线 surge arrester coupling capacitor voltage transformer test method without removing high voltage connecting lead
  • 相关文献

参考文献5

  • 1DL/T474.5-2006,现场绝缘试验实施导则[P].
  • 2郭波,李大军.500 kV线路避雷器不拆线试验方法探讨[J].电网与水力发电进展,2008,24(6):48-50. 被引量:18
  • 3济南泛华佳业微电子公司.AI-6000型自动抗干扰精密介质损耗测量仪使用说明书[K].
  • 4Instruction Manual for DELTA-2000 10-kV AutomatedInsulation Test Set,MEGGER Rev.D.
  • 5instruction manual for coupling capacitor voltagetransformer,HAFELY TRENCH.

共引文献17

同被引文献12

引证文献2

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部