漠大管道及其多年冻土区域地质灾害风险 被引量:12

Geological disaster risk analysis and management solutions for Mohe-Daqing Oil Pipeline in permafrost regions
原文传递
导出
摘要 漠大管道途经我国纬度最高、极端温度达-52.3℃的高寒地带,是我国第1条完全意义上穿越永冻土区域的大口径长输原油管道,所经过的漠河-加格达奇大杨树段共计440km的管道穿越大兴安岭多年冻土区域,包括连续冻土、不连续冻土和岛状冻土。管道沿线地势北高南低,北部地形起伏较大,沿线为大兴安岭低山、丘陵及河谷地貌,南部为松嫩平原,地形平坦开阔,地理环境复杂,极易发生冻胀融沉、崩塌、热融滑坡、水毁冲蚀(坍岸)等地质灾害。分析了漠大管道穿越冻土区域所面临的热融滑坡、冻胀、融沉以及弯曲、翘曲等特有的地质灾害风险,提出了灾害管理和风险应对措施的建议。 Mohe-Daqing Oil Pipeline,with the highest latitude in China,is the first complete pipeline of China in distance and diameter constructed in permafrost regions,where the lowest temperature in winter is at-52.3 ℃.There are about 440 km-long pipeline(Mohe-Dayangshu section of Jiagedaqi)traversing over the Greater Higgnan Mountains' permafrost regions,which are consisted of the continuous permafrost and discontinuous permafrost including segregated frozen ground.The terrain which the pipeline is located at is higher in the North and lower in the South;great ups and downs are in the Northern area;the mountains,hills and river-valley landforms spread over the pipeline.The Southern area,the Songnen Plain,is flat and open with complicated geographic environment,and the geological disasters such as frost thawing,avalanche,melting landslide,water damage erosion(bank collapse)and so on are easy to happen.All the above risks possible in Mohe-Daqing Oil Pipeline are discussed in the paper.Hazard management and risk mitigation measures are presented.
出处 《油气储运》 CAS 北大核心 2011年第8期621-623,592,共3页 Oil & Gas Storage and Transportation
关键词 漠河-大庆管道 多年冻土 地质灾害 热融滑坡 冻胀 融沉 翘曲 Mohe-Daqing Oil Pipeline,permafrost,geological disaster,risk,mitigation measures
  • 相关文献

参考文献5

二级参考文献49

  • 1潘家华,张德国.阿拉斯加管道(待续)[J].油气储运,1994,13(2):1-7. 被引量:12
  • 2李南生,李洪升,丁德文.浅埋集输油管线拟稳态温度场及热工计算[J].冰川冻土,1997,19(1):65-72. 被引量:47
  • 3Lachenbruch A H : Some Estimates of the Thermal Effects of a Heated Pipeline in Permafrost, Geological Survey Circular 632, Washington, DC, 1970.
  • 4Alyeska Pipeline Service Company:Summary Project Description of the Trans Alaska Pipeline Systems August, 1971.
  • 5Johnson T C,McRoberts E C and Nixon J F.. Design Implications of Subsoil Thawing, In:Frost Action and Its Control,Technical Council on Cold Regions Engineering Monograph,Edited by R L Berg and E A Wright,ASCE,New York, 1984.
  • 6Speer T L,Watson G H and Rowley R K.. Effects of Groundice Variability and Resulting Thaw Settlements on Buried Warm-oil Pipelines, In:Proceedings, North American Contribution, 2nd International Conference on Permafrost, Yakutsk,1973.
  • 7AGRAEarth and Environmental Limited & Nixon Ltd: Monograph on Norman Wells Pipeline Geotechnical Design and Performance, Final Report to Department of Natural Resources, March 1999, Geological Survey of Canada Open Files 3773.
  • 8Burgess M M:Analysis of the Pipe and Ditch Thermal Regime,Norman Wells Pipeline, In Proceedings of the 11st International Conference on Offshore Mechanics and Arctic Engineering,Calgary Book No, H0744B,V(A),1992.
  • 9Burgess M M and Lawrence D E: Thaw Settlement in Permafrost Soils: 12 Years of Observations on the Norman Wells Pipeline Right-of-way, In Proceedings of the 50th Canadian Geotechnical Society Conference, Ottawa, 1997.
  • 10Burgess M M & Tarnocai C:Peatlands in the Discontinuous Permafrost Zone Long the Norman Wells Pipellne,Canada, In Proceedings of the International Symposium on Physics, Chemistry and Ecology of Seasonally Frozen Soils, Fairbanks,Alaska, US Army Cold Regions Research and Engineering Laboratory,CRREL Special Report 97-10,1997.

共引文献49

同被引文献85

引证文献12

二级引证文献66

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部