白云隧道突水、突泥段施工技术 被引量:16

Coping with Mud/water Bursting in Tunnel Construction:Case Study on Baiyun Tunnel
在线阅读 下载PDF
导出
摘要 白云隧道地质情况极为复杂,同时穿越F1,F2及F3 3个断层。在开挖至D3K334+733时发生了突水、突泥,为了消除其给施工安全和施工进度带来的极大影响,通过迂回导坑对隧道突水、突泥地段进行横向注浆及设置横向管棚,并结合正洞内全断面帷幕预注浆和大管棚,对该段进行了注浆堵水和加固处理。实践证明,所采用方法合理有效,拱顶沉降控制在合理范围,最终安全地通过了隧道突水、突泥段。 Crossing F1 fault,F2 fault and F3 fault,Baiyun tunnel has extremely complex geological conditions.Mud/water bursting occurs when the tunnel excavation reaches D3K334+733,which has great impact on the construction safety and construction progress.Transverse grouting and transverse pipe roof for the mud/water bursting tunnel section are executed from inside the bypass gallery and full-face curtain grouting and large pipe roof are executed from inside the main tunnel.In such way,successful water-sealing grouting and consolidation are made for the mud/water bursting tunnel section.In the end,the excavation crosses the mud/water bursting section safely.
作者 周军伟
出处 《隧道建设》 2011年第4期504-509,共6页 Tunnel Construction
关键词 白云隧道 断层 突水突泥 迂回导洞 横向注浆 横向管棚 Baiyun tunnel fault mud/water bursting bypass gallery transverse grouting transverse pipe roof
  • 相关文献

参考文献6

二级参考文献43

共引文献136

同被引文献193

引证文献16

二级引证文献320

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部