摘要
浅埋暗挖法的核心是新奥法的基本原理,即在施工中采用辅助措施加固围岩,可以有效地抑制围岩过大变形。从地层适应性、断面形式、施工安全和质量及施工技术四个方面比较地下工程施工方法的优缺点,说明浅埋暗挖法城市地下工程的施工适应性,并且预测其发展前景良好。
The core of shallow underground excavation method is the basic principle of New Austrian Method,which is using auxiliary measures to reinforce surrounding rock during the construction in order to inhibit deformation effectively.The advantages and disadvantages of underground engineering construction methods are compared from aspects of stratum adaptability,cross section form,construction safety and quality as well as techniques to illustrate the construction compatibility of SUEM in city underground engineering and its developing prospect is predicted.
出处
《交通标准化》
2011年第9期64-68,共5页
Communications Standardization
关键词
浅埋暗挖法
施工适应性
展望
shallow underground excavation method
construction compatibility
prospect