摘要
循环冷却水及核安全用水的取排水设施是核电站的重要组成部分。本文着重介绍岭澳核电站水工模型试验中发现的取水明渠在大浪作用下产生长周期水面波动的问题及解决办法。其次对连云港核电站独具特色的排水方案的试验研究结果进行简单论述。
During the physical model test of Ling'ao Nuclear Power Station's water intake and open aqueduct canal, it is discovered that affected by billow there is long period surface fluctuation in the open aqueduct canal and in front of the pump house, which effects seriously the project's safety. In this paper, the producing reasons of the long period fluctuation are analyzed emphatically, and some measures of decreasing the amplitude of long period fluctuation and insure the safety of pump house and factory area are introduced.
出处
《海洋技术》
1999年第4期103-105,共3页
Ocean Technology
关键词
核电站
取排水工程
长周期水面波动
模型试验
nuclear power station open aqueduct canal water intake long period fluctuation