摘要
叙述了谏壁电厂 300 M W 7 号机组热控系统以分布控制系统( D C S)的改造为中心,并辅以其它热控设备和系统配套的相应改造,达到提高机组自动化水平。
With DCS as main project,the I&C system retrofit of Jianbi Power Plant's No.7 300 MW unit is decribed.Other auxilliary control systems were also retrofitted for overall enhancement of the automation level of the unit.
出处
《华东电力》
1999年第9期24-27,共4页
East China Electric Power
关键词
汽轮发电机组
热控系统
改造
DCS
DCS data acquisition coordinating control sequencial control