摘要
第一部分从深部矿井开采的实 际出发,阐述了在深 部矿井的开采的 地压控制应当采 用新设备和新材料及新工艺。第二部分结合国 家“九·五”攻关 课题,叙述了液压支 柱临时护顶高水 速凝尾砂胶结充填采矿方法在湘西金矿深井薄矿脉回采中
The first part of this paper,according to the practical production and development in the deep mine,expounds the requirement of new materials,new procession and new equipment for the control of high underground pressure.The second part elaborates a new mining method of the utility of hydrolic props to support roof and the filling of open area with the solidity formed by quick-condense of high-water materials mixed with tailings.Then discusses its luminous application prospects.
出处
《西部探矿工程》
CAS
1999年第5期52-55,共4页
West-China Exploration Engineering
关键词
地压
地压控制
水力支撑器
金矿
深井开采
underground pressure underground pressure control hydrolic props open area diposition The gelation filling by high-water materials and tailings