本文论述广州抽水蓄能电站二期机电安装工程水泵水轮机/发电电动机组轴系各部件、推力轴承及推力头的安装,简要介绍轴系各部件的结构,并根据机组整体盘车及轴线调整的实践。
This paper gives an account of the erection of each component of the main shaft system, thrust bearing and thrust block of the pump turbine/generator unit, and presents the structure of each component of the main shaft system in the mechano-electric equipment erection works for the Phase-II Guangzhou Pumped-storage Hydroplant. The author also briefs the study result of the throw definition of the generating unit based on the practice of barring the whole unit and readjusting its shaft axis.
出处
《云南水力发电》
1999年第2期20-23,共4页
Yunnan Water Power