广佛线盾构隧道管片处理中冻结法封水的监测分析 被引量:1

Monitoring of Freezing Method Applied to Seal Water Leakage of Shield Tunnel Segments on Guangzhou-Foshan Railway
在线阅读 下载PDF
导出
摘要 珠江三角洲城际快速轨道交通广州至佛山段普君北路站—朝安站区间在管片处理冻结封水工程施工中,对冻结盐水温度、冻土温度、冻胀压力等方面进行了跟踪监测。通过对监测结果进行分析研究,获得了冻结盐水温度、冻土温度、冻胀压力的变化规律,在此基础上对冻结施工过程提出了建议。 Freezing method was applied to seal water leakage of shield segments on the section from Pujun North Road Station to Chao'an Station on Guangzhou to Foshan inter-city rapid rail transit on Zhujiang River delta.During the construction,the temperatures of salty water and frozen soil,the frost heave pressures of soil were surveyed and monitored,and their variation regulations were examined.Based on these studies,some suggestions for freezing work are put forward,which can be severed as a guidline for similar projects.
出处 《现代隧道技术》 EI 北大核心 2011年第1期99-102,共4页 Modern Tunnelling Technology
关键词 基坑工程 冻结法 温度监测 Foundation pit Freezing method Temperature monitoring
  • 相关文献

参考文献3

二级参考文献4

共引文献37

同被引文献10

引证文献1

二级引证文献1

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部