摘要 以金婺大桥边跨4号索换索方案为工程背景,将理论计算与实测相结合,研究单侧卸索(加支撑)、单侧卸索(不加支撑)、双侧卸索(加支撑)和双侧卸索(不加支撑)等卸索方案对斜拉索索力、主梁和桥塔的弯矩、位移及应力的影响。分析表明:单侧卸索会增加桥塔的弯矩,不加支撑也会增大主梁的弯矩。建议采用在边跨主梁和中跨主梁与4号索对应的横隔梁下加竖向支撑的双侧全松+全紧的换索方案。 Based on cable replacement of number 4cable of Jinwu bridge,theory calculation and measured data were combined.Some schemes were studied including unilateral cable replacement without sustainment,unilateral cable replacement with sustainment,symmetrical cable replacement with sustainment,symmetrical cable replacement without sustainment.How different schemes effect the cable force,the bend moment,displacement and stress of main beam and bridge tower were researched.The study showed bend moment of tower increased for unilateral cable replacement scheme and moment of main beam bend increased for cable replacement scheme without sustainment evidently.At last,symmetrical number 4cable replacement scheme with vertical sustainment were suggested and the sustainment was installed on transverse diaphragm of box beam corresponding to number 4cable.
作者 周立
出处 《钢结构》 2011年第1期55-59,共5页 Steel Construction
关键词 金婺大桥 换索方案 索力 有限元 bridge of Jinwu cable replacement scheme cable force finite element
  • 相关文献

参考文献7

二级参考文献8

  • 1王文涛.斜拉桥换索工程[M].北京:人民交通出版社,1996..
  • 2谭晓琦,等.保山地区三达地怒江大桥检测报告[R],2002.
  • 3同济大学建筑设计研究院.云南保山三达地怒江大桥修复工程施工图设计[Z],2003.
  • 4谭晓琦,等.斜拉桥换索监测监控技术研究[Z].2005.
  • 5东南大学力学研究所.保山三达地怒江大桥锚具及高强钢丝锈蚀程度检测报告[R],2003.
  • 6王文涛.斜拉桥换索施工[M].北京:人民交通出版社,1996.
  • 7.Recommendations For Stay Cable Design[]..
  • 8朱战良.广东九江大桥换索技术[J].中外公路,2003,23(5):20-24. 被引量:18

共引文献125

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部