摘要
根据电缆交接试验规范规定和施工现场的实际情况,结合220kV某牵引变电站电缆线路工程,详细介绍了对于电缆距离较长、交叉互联段较多的220kV电缆交接试验的试验项目时间的安排、试验安全措施、试验仪器设备的选择及试验方法的制定。
According to the cable transfer of test specification and the actual situation of the construction site, with 220 kV traction cable line project, the cable from the long, cross - section of more interconnected, a detailed description of the 220 kV cable pilot projects take - over test timing, the choice of test equipment and test methods development ; test security measures were intradueed.
出处
《上海电器技术》
2010年第4期11-16,共6页
Shanghai Electric Appliance Technology
关键词
交接试验
试验设备
试验方法
安全措施
take -over test test equipment test method safety measures