深孔预应力锚索在东风水电站右坝肩边坡加固中的应用 被引量:3

Application of Pre-stressed Anchorage Cable with Deep-hole in Slope Reinforcement on the Right Abutment of Dongfeng Hydropower Station
在线阅读 下载PDF
导出
摘要 东风水电站右坝肩边坡加固处理采用了全锚索处理方案,锚索平均深度约70 m,最深为92 m。由于坝肩岩体卸荷裂隙发育、溶蚀现象严重,施工中存在100 m级高排架施工难、成孔难、孔斜控制难、注浆难等诸多技术难题,通过对深孔预应力锚索施工技术进行攻关研究,使得工程加固处理得以顺利实施。其施工经验值得在喀期特地区类似边坡的加固处理中推广应用。 The treatment scheme with full anchorage cable was adopted in reinforcement treatment on the right abutment of Dongfeng Hydropower Station.The average depth of anchorage cable is about 70 m and the most depth is 92 m.Due to the well development and serious corrosion of unloading fissures of abutment rock mass,there are some technological problems,such as hard construction of high bent with 100 m grade,hard forming hole,hard controlling hole inclination,hard grouting,and so on.Through studied the key construction technology of pre-stressed anchorage cable with deep-hole,the reinforcement treatment was implemented successfully.The construction experience is worth popularizing to similar slope reinforcement treatment in Karst areas.
出处 《贵州水力发电》 2010年第6期15-19,共5页 Guizhou Water Power
关键词 水利水电工程施工 深孔预应力锚索 边坡加固处理 东风水电站 conservancy and hydropower projects construction pre-stressed anchorage cable with deep-hole slope reinforcement treatment Dongfeng Hydropower Station
  • 相关文献

同被引文献13

引证文献3

二级引证文献8

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部