摘要
编制露天矿生产计划是当前采矿工程中不可或缺的环节,当前以DIMINE矿业软件为平台编制的适应于国内露天矿的采剥计划系统,立足实际的生产数据,考虑多种因素,有效地指导露天矿山分期开采或中长期采剥计划的编制,为采掘生产计划优化工作提供了切实可行的新途径,提高了矿山生产效率,达到迅速开展工作的目的。
Making production plan of open-pit mine is an indispensable link in mining engineering nowadays.Considered many factors,the research of stripping plan system based on DIMINE mining software can effectively guide the design of mining stage or mid-long term production plan on open-pit mine standing on the actual production data..It can provide new workable way for stripping plan optimization,meanwhile,it improves the production efficiency.
出处
《中国钼业》
2010年第6期12-15,共4页
China Molybdenum Industry
关键词
三维可视化
露天矿山
生产采剥计划
效率
3D visualization
open-pit mine
production stripping plan
efficiency