摘要
本文以八一农大理化楼工程实践为例,介绍用坑探弥补钻探所取数据的不足,有效的提高了地基土的设计承载能力,从而降低了工程造价.这种方法对同类工程十分有用。
The pit probe method is used in the foundation processing of the physicaland chemical building of the August First Land Reclamation University. This methodovercomes the drawbacks of the drilling method so as to decrease the engineeringcost. The pit probe method has promising practical use for such kind pro,ects.
出处
《黑龙江八一农垦大学学报》
1999年第1期48-50,共3页
journal of heilongjiang bayi agricultural university
关键词
钻探
坑探
淤泥质土
地基土承载能力
Drilling
Pit probe
Silt foundation
Carrying capacity