坂田工商所综合楼人工挖孔桩桩端土层的处理

The Processing to the Layer at the End of the Man-Digged Filling Pile in Composite Building of Industrial and Commercial Bureauin Ban Tian
在线阅读 下载PDF
导出
摘要 本工程的人工挖孔桩在挖孔过程中遇到含泥质砾砂层发生流砂而无法施工.作者提出用高压注浆法旋喷加固含泥质砾砂层和粘土层,形成直径1.6~1.8m、高度6~8m的圆柱形复合土体作为桩端持力层,符合单桩承载力设计要求. There is muddy gravel sand when excavating the man-digged filling piles. It is difficult to construct because of drift sand. We used grout jetting under high pressure to reinforce the muddy gravel sand and clay, and formed cylindrical reinforced soil with 1.6-1.8 meters diameter and 6-8 meters height as forced layer at the end of the pile. The results accord with the demands of design.
作者 吴新生 陈荣
出处 《南方冶金学院学报》 1999年第2期74-77,共4页 Journal of Southern Institute of Metallurgy
关键词 人工挖孔桩 桩端持力层 复合土体 桩基 man-digged filling pile, forced layer at the end of the pile, reforced soil
  • 相关文献

参考文献2

  • 1《工程地质手册》编写委员会.工程地质手册(第三版)[M].北京:中国建筑工业出版社,1992..
  • 2《地基处理手册》编写委员会.地基处理手册(第一版)[M].,1998.346-374.

共引文献22

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部