五龙金矿76#脉难采矿体的开采实践

Mining practice of the orebody which is hard to mine in No.76 vein of Wulong Gold Mine
在线阅读 下载PDF
导出
摘要 针对上下盘围岩不稳固的五龙金矿76#脉难采矿体,通过采用静态留矿法开采,配合全采场锚杆金属网工艺护盘技术,解决了在回采过程中安全问题和二次贫化过大的技术难题,提高了矿房生产能力,减轻了工人劳动强度,给矿山带来了可观的经济效益。 The country rocks in upper and lower walls of the orebody in No.76 vein of Wulong Gold Mine are unstable,so it is hard to mine.Employing static shrinkage method with the cooperation of the technique of protecting wall by means of metal strip bolt network in the whole stope,the question of safety and the difficult technical problem of too great secondary dilution are solved.As a result,the production capacity in the stope is improved ,the intensity of labor is reduced and the considerable economic benefits are brought about.
机构地区 辽宁五龙金矿
出处 《黄金》 CAS 北大核心 1999年第6期24-28,共5页 Gold
关键词 分段空场法 静态留矿法 金矿 采矿 难采矿体 secondary dilution sublevel open stope method static shrinkage method protecting wall by means of metal strip bolt network economic evaluation
  • 相关文献

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部