摘要
对国内首台专门为燃烧奥里油设计生产的600 MW某奥里油发电厂锅炉进行了介绍,对该电厂带不到设计负荷、输灰系统不畅、空气预热器堵塞的原因进行了分析,同时对解决这些问题的方法进行了探讨,并介绍了湛江奥里油电厂实际解决这些问题的方法和效果。
The boiler of 600 MW orimusion oil power station particularly designed and builded for burning orimusion oil is introduced in this paper, the probems of cannot getting to designed load and transport ash system blocking and air heater blocking for the power plant are analyzed. At the same time, the methods of solving the problems are discussed. At last, zhanjiang power plant' methods and effects of solving the problems in fact are introduced.
出处
《锅炉技术》
北大核心
2010年第5期59-63,共5页
Boiler Technology
关键词
奥里油
输灰系统
锅炉
orimusion oil
transport ash system
boiler