丹江口大坝加高左岸工程主要由左岸土石坝段和混凝土坝段组成。文章主要介绍丹江口大坝左岸土石坝段初期工程与混凝土坝段连接部位加固的施工工艺、技术要求和所需材料的物理性能指标。
The heightening left bank works of Danjiangkou project consists of earth rock dam and concrete dam section on left bank. The paper mainly introduces construction technique, technique demand and physical perfor-mance index of construction material of strengthening junction part between the earth rock dam and concrete dam during the initial construction for the earth rock dam of left bank of Danjiangkou reservoir.
出处
《东北水利水电》
2010年第9期13-15,共3页
Water Resources & Hydropower of Northeast China
关键词
混凝土坝
防渗墙
加固
土石坝
concrete dam
cutoff wall
strengthening
earth rock dam