摘要
在深入研究既有小净距隧道设计施工成功经验的基础上,针对某山岭隧道的特点提出了其设计施工的原则和完整的设计参数,并重点讨论了隧道施工工序的选择,在深入论证的基础上提出一套科学合理的隧道施工工序,以指导类似工程的实施。
On the basis of deep studying of existed successful experience of clear distance designing,it provides the constructional principle and integrated design parameter according to the character of a mountain tunnel,and mainly discusses about the process-selecting of the tunnel construction,on the basis of in-depth demonstration,it proposes a set of scientific and rational tunnel construction procedure,which will be constructive for the similar construction.
出处
《山西建筑》
2010年第17期336-338,共3页
Shanxi Architecture
关键词
小净距
岩体加固
设计荷载
施工工序
爆破
clear distance
reinforce the rock mass
design load
construction process
blast