为满足湘西地区用电需求并缓解湘南受端系统的供电压力,怀化石煤发电工程将在2012年建成投产。研究表明,怀化石煤发电工程通过剖进艳山红-宗元500kV线路接入系统是适宜的。
To meet the load demand of Xiangxi district and alleviate the supply pressure of Xiangnan power grid,Huaihua Stone-coal power plant is to be up and running in 2012.The study concludes that it is adaptable for Huaihua Stone-coal power plant to connect the Hunan power grid cutting through Yanshanhong ~ Zongyuan 500 kV tranmission lines.
出处
《华中电力》
2010年第1期19-22,共4页
Central China Electric Power
关键词
怀化石煤电厂
接入系统方案
潮流迂回
安全稳定
综合年费用
huaihua stone-coal power plant
connection to the grid
load by pass
security and stability
overall annual cost