多项目无节奏流水施工时间成本置换优化分析 被引量:1

Optimization Modeling and Solution about Discrete Time-Cost Trade-off Problem in Non-rhythm Flow Process with Multi-project Condition
在线阅读 下载PDF
导出
摘要 无节奏流水施工是施工组织的常见形式。文章考虑了多项目环境下多模式的无节奏流水施工组织,并结合传统的time-cost置换问题进行了建模求解。目标函数直接采用双目标形式,并基于NSGA-Ⅱ非劣排序思想进行了算法设计。仿真测试表明,改进的算法能够有效的获得较优的离散time-cost曲线,可以为复杂环境下的无节奏流水施工组织与实施提供决策支持。 Non-rhythm flow process is a general pattern for construction organization. Considering the non-rhythm flow process under the conditions of multi-project and multi-mode, this paper modeled the problem combing with conventional discrete time-cost trade-off. The objective function adopted bi-objective expression. The algorithm was designed based on NSGA- Ⅱ methodology. The simulation results show that the improved algorithm can get the optimal discrete time-cost curve, which can provide decision making support for the construction organization and implementation in non-rhythm flow process under the complex environment
出处 《工程管理学报》 2010年第2期156-159,共4页 Journal of Engineering Management
基金 国家自然科学基金重点项目(70631003) 国家自然科学基金(70871034) 国家"863"项目(2006AA04A126)
关键词 无节奏流水施工 多项目 多模式 time—cost置换 NSGA—Ⅱ non-rhythm flow process multi-project multi-mode time-costtrade-off NSGA-Ⅱ
  • 相关文献

参考文献10

  • 1彭武良,王成恩.一种多模式资源受限的离散时间成本平衡问题[J].东北大学学报(自然科学版),2008,29(8):1077-1079. 被引量:3
  • 2方良平,姜炜.无节奏流水施工方法在施工顺序优选中的应用[J].山西建筑,2008,34(14):207-208. 被引量:5
  • 3任宏,蔡伟光.无节奏流水施工优化模型及其动态规划算法[J].重庆大学学报(自然科学版),2007,30(5):135-137. 被引量:9
  • 4B.Jarboui,N.Damak,P.Siarry,A.Rebai.A combinatorial particle swarm optimization for solving multi-mode resource-constrained project scheduling problems. Journal of Applied Mathematics . 2008
  • 5Mika M,Waligora G,Weglarz J.Tabu search for multimode resource-constrained project scheduling with schedule-dependent setup times. European Journal of Operational Research . 2008
  • 6Mohammad R Ranjbar,Fereydoon Kianfar.Solving the discrete time/resource trade-off problem in project scheduling with genetic algorithms. Journal of Applied Mathematics . 2007
  • 7Deb K,Pratap A,AgarwalS,Meyarivn T1.A fastand elitist multi-objective genetic algorithm. NS-GA-Ⅱ.IEEE Transactions on Evolutionary Compu-tation . 2002
  • 8Spears W.M,DeJong K.A.On the Virtues of Parameterized Uniform Crossover. Proceedings of the Fourth International Conference on Genetic Algorithms . 1991
  • 9Chang PeiChann,,Hsieh JihChang,Wang ChihYuan.Adaptive Multi-objective Genetic Algorithms for Scheduling of DrillingOperation in Printed Circuit Board industry. Applied Soft Computing . 2007
  • 10Ranjbar,M.et al.A hybrid scatter search for the discrete time/resource trade-off. European Journal of Operational Research . 2007

二级参考文献17

  • 1韩英爱,高志通.建筑工程流水施工流程优化问题探讨[J].长春工程学院学报(自然科学版),2002,3(3):60-62. 被引量:8
  • 2雷建平,袁刚,袁细发.单亲遗传算法与流水作业优化[J].武汉理工大学学报(交通科学与工程版),2004,28(4):593-596. 被引量:9
  • 3苏银申.无节奏流水科学化途径[J].重庆交通学院学报,1997,16(2):114-122. 被引量:1
  • 4编写组.运筹学(修订版)[M].北京:清华大学出版社,1990..
  • 5毛鹤琴.土木工程施工.2版[M].武汉:武汉理工大学出版社,2004.
  • 6王早生.房屋建筑工程管理与实务[M].北京:中国建筑工业出版社,2004.
  • 7Hindelang T J, Muth J F. A dynamic programming algorithm for decision CPM networks[J ]. Operations Research, 1979, 27(2) :225 - 241.
  • 8Prabuddha D E, Durme E J, Ghosh J B, et al. Complexity of the discrete time-cost trade-off problem for project networks [J ]. Operations Research, 1997,45(2):302- 306.
  • 9Demeulemeester E, De Reyck B, Foubert B, et al. New computational results on the discrete time/cost trade-off problem in project networks[J ]. Journal. of the Operational Research Society, 1998,49(6) : 1153 - 1163.
  • 10Skutella M. Approximation algorithms for the discrete time-cost trade-off problem [ J ]. Mathematics of Operations Research, 1998,23 (4) : 909 - 929.

共引文献13

同被引文献10

引证文献1

二级引证文献19

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部