摘要
文中介绍针对大唐淮北发电厂8号汽轮机效率低问题进行的汽轮机组效率优化工作,阐述了经过现场调查、调整、试验等阶段找到影响该汽轮机效率的因素,从系统调整、设备改进和生产管理3方面采取有效措施予以消除,提高了汽轮机组的运行效率。
To solve the problem of low efficiency of the No8 steam turbine,HuaiBei power plant carried out the improvement of efficiency of the No8 steam turbine. By searching,adjustment and experiment in workshop,elements which impaired the efficiency of the turbine were found and then undone by enforeing measures in three sides of adjusting system,upgrading equipment and management,so that efficiency of the turbine was promoted.
出处
《安徽电力》
2009年第4期55-58,共4页
Anhui Electric Power
关键词
发电厂
汽轮机
运行
效率
优化
power plant
steam turbine
efficiency
operation
optimization