摘要
打破传统的施工方式,采取有效的安全技术措施将竖井施工场地与井塔施工场地分开,组织竖井井筒与井塔上下同时施工,大大缩短施工工期。
Breaking free from the traditional approach, this method used effective and safety technical measures to construct the shaft and derrick at the same time with a separate shaft site and a separate derrick site. The techniques will greatly shorten the construction period.
出处
《中国矿山工程》
2009年第5期1-4,41,共5页
China Mine Engineering
关键词
竖井
井塔
同时施工
shaft
derrick
construction at the same time