摘要
重点介绍京杭运河徐扬段续建二期工程邳州停泊锚地靠船墩水下钻孔灌注桩及承台施工中的重点工序和施工方法,得出了该工程施工方法经济效益显著且能保证工程质量的结论。
The critical procedures and construction methods of underwater cast-in-place bored piles and cushion cap of Pizhou anchorage place dolphin belonged to Xu-Yang stage continued building second engineering of Jing-Hang canal were introduced critically.It concluded that the engineering construction method was economical and guaranteed engineering quality.
出处
《山西建筑》
2009年第33期99-100,共2页
Shanxi Architecture
关键词
水下钻孔灌注桩
承台
施工工艺
underwater cast-in-place bored piles
cushion