摘要
居甫渡水电站大坝溢流坝段4个中墩为宽尾墩,配备4套液压滑升模板,4个宽尾墩混凝土浇筑同步施工,满足了施工进度计划和安全度汛节点工期的要求。
The 4 middle piers of the overflow section of the Jufudu dam are all of flaring type and 4 sets of hydraulic climbing forms were provided for their construction. The concreting work of the 4 flaring piers was done simultaneously, which satisfied the requirements of both construction schedule and safely tiding over the flood period.
出处
《云南水力发电》
2009年第4期89-91,共3页
Yunnan Water Power
关键词
居甫渡水电站
宽尾墩
滑模施工
Jufudu Hydropower Project
flaring pier
slip- form construction