摘要 马鞍山长江公路大桥施工桥位处地下水非常丰富,为验证在有水环境下根键顶进施工的可行性,在施工现场针对1个根式基础进行根键水下顶进试验。沉井首先下沉到位并封底,在干环境下安装好根键,然后灌满水,由潜水员下潜至预定位置,利用千斤顶进行根键顶进。试验结果表明,水下项进根健顺利、安全,单根根键顶进时间为12h,比干环境长6~8h,顶进过程未出现异常现象。水下顶进根键可行。 The underground water at the site of Maanshan Changjiang River Highway Bridge is very abundant. To verify the feasibility of jacking root studs of the root type caisson foundation in the environment with water, the test for jacking the studs of a caisson foundation of such type under water was made in the field. The caisson was first sunk to its designed elevation and the bottom sealing for the caisson was done. The studs were installed in the caisson the dry environment and the caisson was filled with water. The diver then dived into water to the designated place in the caisson where he would jack the studs into the soil outside the caisson. The results of the test show that the jacking of the root studs under water is smooth and safe. The time for jacking of a single stud is 12 h which is 6-8 h longer than that of a stud in the dry environment. In the process of jacking, no abnormalities happened and the jacking of the studs under water is feasible.
出处 《桥梁建设》 EI CSCD 北大核心 2009年第A01期73-75,共3页 Bridge Construction
关键词 马鞍山长江公路大桥 桥梁基础 根式基础 根键 水下顶进 试验 Maanshan Changjiang River Highway Bridge bridge foundation root type caisson foundation root stud jacking under water test
  • 相关文献

参考文献2

二级参考文献5

共引文献19

同被引文献23

引证文献2

二级引证文献2

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部