摘要
介绍了瀑布沟水电站深覆盖层基础的处理方案及关键技术,并通过监测资料分析,得出瀑布沟水电站的基础处理满足工程要求的结论。
This paper introduces the key technique and treatment scheme of the foundation under the deep cover in Pubugou hydropower station, and addresses the conclusion which met the engineering requirement for the foundation treatment through the analysis of monitoring data.
出处
《吉林水利》
2009年第8期41-43,48,共4页
Jilin Water Resources
关键词
深覆盖层
基础处理
监测
瀑布沟水电站
Deep cover
foundation treatment
monitoring
Pubugou hydropower station