摘要
贵港电厂一期工程(2×600 MW)是广西首个投产发电的600 MW级超临界机组工程,两台机组分别于2007年2月和2007年7月投入商业运行。通过两年来除灰系统的投运情况,对灰渣系统的设计、设备的选用等方面做出小结,供同行参考。
Phase I project (2 × 600 MW) of Guigang Power Plant is the first project of Guangxi with 600MW supercritical unit put into operation to generate electricity, whose two units were put into commercial operation in Feb. and July of 2007 respectively. The design of ash-slag handling system and equipment selection is dis- cussed based on operational conditions of the system over the past two years.
出处
《红水河》
2009年第4期36-40,共5页
Hongshui River
关键词
除灰系统
设计
运行
贵港电厂
ash handling system
design
operation
Guigang power plant