摘要
针对目前老电厂脱硫工程改造中如何充分利用原有的静电除尘装置这一问题,进行新的设计和尝试,采用半干法脱硫工艺和电-袋串联式收尘器的组合形式,不仅解决了场地不足的问题,而且还充分利用原有的静电除尘器,大大降低了成本,同时脱硫效果也能完全满足设计要求。
Against the problem of how to make full use of electrostatic precipitator in the old power plant alteration, new design and attempts were made. Using semidry method desulfurization process and electrostatic precipitator combined with bag filter, it's not only resolved the space problem, but also made full use of electrostatic precipitator. This alteration saved a lot of cost and the desulfurization performance could also meet the design request.
出处
《能源工程》
2009年第3期48-50,共3页
Energy Engineering