摘要
结合具体工程实例,介绍了地质超前预报的方法和内容,深入探讨了超前地质预报在大瑶山三号隧道施工中的应用,展望了超前地质预报工作的前景,从而推广超前地质预报的发展和应用。
Combining with concrete example, the author introduces the method and content of advance geology forecast, deeply discusses the application of advance geology forecast on Dayao mountain the third tulmel construction, prospects the future of advance geology forecast work, thus promoting the development and application of advance geology forecast.
出处
《山西建筑》
2009年第12期336-338,共3页
Shanxi Architecture
关键词
超前地质预报
实施方案
处理措施
advance geology forecast, implementation scheme, treatment measure