综采工作面坚硬顶板处理 被引量:3

Hard Roof Treatment of Fully Mechanized Coal Mining Face
在线阅读 下载PDF
导出
摘要 介绍了处理综采工作面坚硬顶板的两种方法:强制放顶法和压力注水弱化顶板法,分析了两种方法的效果及优缺点,论述了两巷断顶法的工艺方法和深孔爆破参数的选择,探讨了压力注水弱化顶板的机理和注水孔的布置及压力注水工艺。 Introduces two methods of treating hard roof of fully mechanized mining face : enforced top coal caving method and pressure water injection weaken roof method, analyses the effects and the advantages and disadvantages of the two methods, elaborates the technique and selection of the deep hole blasting parameters of two roadways break tip roof method, discusses the mechanism of pressure water injection weaken roof and the arrangement water injection hole as well as the process of pressure water injection.
作者 芦勇
出处 《山西焦煤科技》 2009年第2期25-27,共3页 Shanxi Coking Coal Science & Technology
关键词 坚硬顶板 爆破放顶 压力注水弱化 工艺 分析 效果 Hard roof Blasting top coal caving Pressure water injection weaken Process Analysis Effect
  • 相关文献

参考文献3

  • 1靳钟铭,徐林生.煤矿坚硬顶板控制[M].北京:煤炭工业出版社,1998:58-61.
  • 2周维恒.高等岩石力学[M].北京:水利电力出版社,1990..
  • 3钱鸣高 刘听成.矿山压力及其控制[M].北京:煤炭工业出版社,1994..

共引文献20

同被引文献26

引证文献3

二级引证文献27

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部