摘要
论述某商住楼人工挖孔桩基础工程,经检测发现桩基工程存在承载力不足和桩身质量问题。根据桩基工程检测、钻探和施工资料,综合分析事故原因,提出基础的补救措施,并取得良好的使用效果。
In this paper ,a practical project with hand-dug cast  ̄in-situ pile foundation is introduced. The results of pile static load test and dynamic test showed the insufficency of pile vertical bearing capacity and the shaft defect problem. Based on the test ,geological conditions and construction material , remedical measures were adopted after comprehensively analysing the accident causes. In treating the problem , pile-soil interaction was taken into account. The good effects of use and economy were gained.
出处
《岩土工程学报》
EI
CAS
CSCD
北大核心
1998年第2期63-65,共3页
Chinese Journal of Geotechnical Engineering
关键词
人工挖孔桩
工程质量
承载力
补救措施
处理
hand-dug cast-in-situ pile ,pile static load test ,dynamic pile test , settlement.