摘要
本文对基建工程量应包括的内容:满足采金船组建的工业场地、保有与生产能力相适应的储备矿量、采金船出坑等有关的工程项目(基建探矿、基建剥离、采金船出坑、尾矿推平、基坑供排水等)给出了计算公式,试图合理确定并统一基建工程量的计算口径.
This paper has formulated the amount of capital works including the construction of working site of dredge operation, the conservation of reserves of ore needed to meet productive capacity, the excavation for the dredge dock and the related capital construction project such as drill-hole surveying, pre-production stripping, leveling of tailing, water supply and drainage system of dock etc.The author of this paper tries to definite and unify the calculation of the amount of capital works reasonably.
出处
《黄金》
CAS
北大核心
1990年第1期16-20,共5页
Gold
关键词
采金船矿山
基建工程量
确定
mine field of dredge work
amount of capital works
ore reserve
reasonable definition