摘要 结合水电站工程实例,在现场调查和工程地质勘察结果的基础上,详细分析某隧道的裂缝形成原因,主要是1885m高程以上边坡失稳的影响、地应力的作用、1885m以下边坡的不当开挖、动静荷载和施工渗水等几种因素,排除了混凝土干缩和温度应力两个影响因素。 This paper combined with one of the southwest China hydropower Projects,and on the basis of on-site investigations and the results of geological prospecting works, make a detailed analysis for the reasons of the tunnel cracks.And the reasons including the following:the first is the impact of the slope instability above 1885 elevation;secondly,the role of the rock stress;the third is the improper excavation of the slope below the 1885 elevation;the forth reason is the dynamic and the static loads the;last one is the water seepage. Ruled out the factors of the concrete shrinkage and thermal stress.
作者 周峰 郑晓晶
出处 《工程建设与设计》 2008年第12期92-95,共4页 Construction & Design for Engineering
关键词 隧道 裂缝 成因 分析 tunnel cracks factors analysis
  • 相关文献

参考文献5

共引文献7

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部