摘要
介绍了广东平海电厂2×1GW主蒸汽。
The paper outlined the optimum design of the Drainage System in the main steam and rehead steam system in PINGHAI 2×1 GW power plant.
出处
《工程建设与设计》
2008年第11期50-52,共3页
Construction & Design for Engineering
关键词
超超临界
旁路系统
疏水系统
ultra supercritical
steam turbine bypass system
the drainage System