摘要
通过工程实例,介绍了240 m钢筋混凝土烟囱采用液压提模施工工艺的具体施工方案,对烟囱各组成部分的施工要点作了总结,并指出该工程采用液压提升施工工艺,加快了施工进度,取得了良好的经济效益。
Through the engineering example, the paper introduces the concrete construction scheme of 240 m reinforced concrete chimney by using the construction technology of the hydraulic lifting form, summarizes the construction points of the parts of the chimney, and points out that the construction technology of the hydraulic lifting form used in the project accelerates the construction progress and acquires the good economic benefit.
出处
《山西建筑》
2008年第33期134-135,共2页
Shanxi Architecture
关键词
烟囱
液压提模
施工技术
经济效益
chimney, hydraulic lifting form, construction technology, economic benefit