本文就华东电网8回总长1450km的500kV线路的运行概况作了介绍,重点分析了运行中发生的几次事故,提出了防止污闪、倒塔、间隙放电等的技术措施,可供运行部门参考。
This paper summarizes the operation of 8 feeders of 500kV power line, totalling 1450km, in East China Network. The author is stressing on the analysis of a number of faults that happened during operation. Technical
measures of dirt flashover prevention,tower fall-down and gap discharge e■c are proposed.
出处
《华东电力》
1990年第1期1-7,共7页
East China Electric Power