摘要
本文通过对绕阳河干流防洪工程冬季筑堤的沉降进行观测和分析研究,提出了冬季筑堤沉降量的计算方法,为我国北方寒冷地区其他河流下游低洼地区及类似堤防的冬季施工在设计预留沉降量时提供了经验和理论依据。
This paper put forwards the calculation method of the settlement of the embankment constructed in winter, according to the analysis and research of the observation of the dyke settlement constructed in winter on Raoyang River main stream flood control project, and provides experience and theory basis for setting aside settlement amount in the design of the other similar projects in the low--lying areas of downstream in the northern cold area.
出处
《吉林水利》
2008年第8期17-19,共3页
Jilin Water Resources
关键词
绕阳河
冬季筑堤
沉降
Raoyang River, embankment constructed in winter, settlement