以福建大唐宁德电厂一期海水循环冷却水系统工程为例,分析了桩顶注浆加固的施工工艺、施工方法及作用原理,介绍了该次注浆加固的技术参数,并阐述了具体的技术措施和作用效果。
Taking the cooling water system of the seawater circulating in the first phase project of Datang Ningde power plant in Fujian as an example, the author analyzes the construction technology, the construction method and the action principle of the pile block injected reinforcement, introduces the technical parameter of the grouting reinforcement, and describes the concrete technical measures and the action effect.
出处
《山西建筑》
2008年第23期120-122,共3页
Shanxi Architecture
关键词
桩顶
注浆加固
沉井施工
技术措施
pile top, grouting reinforcement, open caisson construction, technical measures