摘要
介绍了锦屏一级水电站化学灌浆试验研究及施工情况,明确在此类地质条件下采用化学灌浆是完全必要且可行的,整个试验取得了成功,对今后工程的实施及类似工程项目的试验研究具有借鉴意义。
Based on an introduction of the testing and construction of chemical grouting at Jingpin I Hydropower Plant, it is concluded that chemical grouting is necessary and feasible under such geological conditions. The success of testing provides reference for construction and testing of similar projects in the future.
出处
《广西水利水电》
2008年第3期8-11,共4页
Guangxi Water Resources & Hydropower Engineering
关键词
化学灌浆
试验
锦屏一级电站
Chemical grouting
test
Jingpin I Hydropower Plant